Wasco County is holding public hearings right now on a proposed Endowment Fund. The idea itself is solid, but the way it’s written doesn’t really give folks a clear sense of just how much money we’re talking about - or what setting that money aside would mean for the county.

Wasco County Endowment per Currently Written Ordinance
The current ordinance language states:

Capitalizes the Fund with up to $15,000,000 from existing County Project Fund balances, plus ongoing county-retained SIP revenues, tax abatement dollars, and investment earnings.

This means the capital being proposed is not just $15,000,000, it’s closer to $78,000,000. Here’s the numbers (these numbers do not incorporate depreciation and reinvestment, actual dollars may vary).

Lisa’s testimony about the planned Endowment Ordinance on August 19th at The Board of County Commissioners Meeting

Google Data Center Revenue - Wasco County

Google Data Center Revenue - Wasco County

All agreements are for 15 years

Agreement Annual
Revenue
Years To
Date
Revenue Paid Years
Remaining
Revenue
Remaining to be
Paid
Total
Revenue
Enterprise Zone Agreement 1 (Signed 2005, has expired) $250,000 15 $3,750,000 0 $0 $3,750,000
Enterprise Zone Agreement 2 (Signed 2013, expires 2031-2032) $280,000 10 $2,800,000 5 $1,400,000 $4,200,000
Enterprise Zone Agreement 3 (Signed 2015, expires 2033-2035) $907,133 7 $6,349,931 8 $7,257,064 $13,606,995

Strategic Investment Program, Agreement 4

(Signed 2021. This includes two data centers. The first center is now making payments, the second center has not yet received occupancy)

SIP Data Center 1 (50% full tax value) Annual
Revenue
Years To
Date
Revenue Paid Years
Remaining
Revenue
Remaining to be
Paid
Total
Revenue
Initial Payment (One Time Fee) $1,500,000 1 $1,500,000 0 $0 $1,500,000
Taxable Portion (Wasco County is 24.4% tax) $379,654 1 $379,654 14 $5,315,156 $5,694,810
Guaranteed Annual Payment (GAP) $2,878,639 1 $2,878,639 14 $40,300,946 $43,179,585
Community Service Fee (CSF) $610,000 1 $610,000 14 $8,540,000 $9,150,000
Total $5,368,293 $5,368,293 $54,156,102 $59,524,395
Revenue Added to Endowment Fund (not including final data center) $62,813,166
Initial Endowment 15,000,000
Total Dollars put into the Endowment $77,813,166

The ordinance includes a 15‐year restriction on using the funds. After that period ends, only a portion of the annual interest can be spent and even that interest comes with additional limits on how it can be used. Any new revenue added to the fund also starts its own rolling 15‐year restriction.

What if an Optional Funding Idea Similar to City of The Dalles SIP Resolution is Considered?

The City of The Dalles passed an ordinance that lays out how money from the Google SIP Agreement will be split out, assigning different components of the agreement to different funds within the city budget (note: none of these have a 15-year “no touch” component). Here’s what their resolution includes (per the city website).

Key elements of the 2024 resolution include:

1. Initial Payment Revenue shall be received in the Special Enterprise Reserve Fund and reserved for proposed special projects.

2. Property Tax Revenue shall be received in the General Fund and used to support general fund operations.

3. Community Service Fee Revenue shall be received in the Capital Improvement Fund until sufficient reserves are established to support the City's General Facility Capital Improvement Plan, then received in the Special Enterprise Reserve Fund for proposed speci projects.

4. Guaranteed Annual Payment Revenue shall be received in the Special Enterprise Reserve Fund and utilized to support City Public Works Master Plan projects. Funds shall be transferred to the appropriate Public Works fund to support said projects as they commence

A similar option for Wasco County could provide a “win-win” situation if funds were assigned to both a Special Investment Fund and the Endowment Fund, utilizing different components of the Data Center agreements.

  • The remaining Enterprise Zone Payments, the SIP Initial Payment and the SIP Community Service Fee go into a Special Investment Fund for Public Works bridge projects and community infrastructure needs, or economic development needs ($1,400,000 + $7,257,064 + $1,500,000 + $8,540,000 = $18,697,064)

  • Property Tax - goes into General Fund

  • The initial Endowment capital plus the SIP Guaranteed Annual Payment goes into Endowment Fund ($15,000,000 + $40,300,946 = $55,300,946)

Here’s what that option would look like, with a second section if it includes the SIP Agreement Data Center 2:

Special Investment Fund & Endowment Revenue

Current Funding Structure

Special Investment Fund Revenue Streams

Source Initial
Investment
Annual
Revenue
Total Investment
Enterprise Zone Agreement 2 Remaining Funds $280,000 280,000 $1,400,000
Enterprise Zone Agreement 3 Remaining Funds $907,133 907,000 $7,257,064
SIP Data Center 1: Initial Payment $1,500,000 $1,500,000
SIP Data Center 1: Community Service Fee (CSF) $610,000 610,000 $8,540,000
Total $3,297,133 1,797,000 $18,697,064

Endowment Revenue

Source Initial
Investment
Annual
Revenue
Total Investment
Initial Payment from County Funds $15,000,000 $15,000,000
SIP Data Center 1: Guaranteed Annual Payment (GAP) $2,878,639 $2,878,639 $40,300,946
Total $17,878,639 $55,300,946

Funding With SIP Data Center 2 Included

Special Investment Fund Revenue Streams

Source Initial
Investment
Annual
Revenue
Total Investment
Enterprise Zone Agreement 2 Remaining Funds $280,000 280,000 $1,400,000
Enterprise Zone Agreement 3 Remaining Funds $907,133 907,133 $7,257,064
SIP Data Center 1: Initial Payment $1,500,000 $1,500,000
SIP Data Center 1: Community Service Fee (CSF) $610,000 610,000 $8,540,000
SIP Data Center 2: Initial Payment $1,500,000 $1,500,000
SIP Data Center 2: Community Service Fee (CSF) $610,000 610,000 $8,540,000
Total $5,407,133 2,407,133 $28,737,064

Endowment Revenue

Source Initial
Investment
Annual
Revenue
Total Investment
Initial Payment from County Funds $15,000,000 $15,000,000
SIP Data Center 1: Guaranteed Annual Payment (GAP) $2,878,639 $40,300,946
SIP Data Center 2: Guaranteed Annual Payment (GAP) $2,878,639 $40,300,946
Total $20,757,278 $95,601,892

A Win for the County Government, and a Win for County Communities

Having the two-fund option provides a better balance of investment for community infrastructure or economic development needs, with funding for an Endowment Fund that provides a future revenue stream that is not tied to property taxes. The county doesn’t have to choose an “all-or-nothing” approach, and adding the Special Investment Fund ensures infrastructure investments are being addressed before the impact of 15 years of inflation.

Contact your County Commissioners Or Make A Public Comment

Commissioners and Contacts
Scott Hege, Commissioner, Chair (Term: January 1, 2023 - Dec. 31, 2026) 
ph: (541) 506-2522 
cell: (541) 288-1616 
Click here to email Scott Hege: ScottH@wascocountyor.gov(Opens in new window)

Rodger Nichols, County Commissioner, Vice-Chair (Term: July 15, 2026 - Dec. 31, 2026)
ph: (541) 506-2523 
cell: (541)980-1728Click here to email Rodger Nichols Rodgern@wascocountyor.gov(Opens in new window)

Jeff Justesen, County Commissioner (Term: January 1, 2025 - December 31, 2028)
ph: (541) 506-2524
cell: (541) 980-2231
Click here to email Jeff Justsen JeffJ@wascocountyor.gov

Submit Public comment to Christine McNamara, Executive Assistant, before or at the September 2nd Meeting of the Board of County Commissioners
Click here to email Christine: ChristineMc@wascocountyor.gov